SPRING 2010 - MIDTERM 2 - SOLUTION
Drainage area = 53 ha Rainfall intensity = 25 mm/hr Runoff coefficient = 0.95 Peak discharge Qp = 0.95 × 25 mm/hr × 53 ha Qp = 0.95 × 25 mm/hr × 0.001 m/mm × (1/3600) hr/s × 53 ha × 10,000 m2/ha Qp = 3.50 m3/s ANSWER. Problem 2 100407
Rainfall intensity = 25 mm/hr
Runoff coefficient = 0.95
Peak discharge Qp = 0.95 × 25 mm/hr × 53 ha
Qp = 0.95 × 25 mm/hr × 0.001 m/mm × (1/3600) hr/s × 53 ha × 10,000 m2/ha
Qp = 3.50 m3/s ANSWER. Problem 2