Guyana Coastal Flood Protection Program
100. Project Reports
101. Guyana: Preliminary damage and needs assessment following the intense flooding of January 2005
102. Task force for infrastructure rehabilitation: Progress report until March 20th 2005
103. Hydrology and water resources interim review - October 2003
104. Infrastructure rehabilitation: Short to medium term plan, First draft
105. Infrastructure rehabilitation: Short to medium term plan, Final Report, 12 July 2005
106. East Demerara and Boereserie Conservancy Dams: Condition assessment by dams specialist
107. Guyana drainage and irrigation systems rehabilitation project - October 2003
108. Final Report of the Special Advisor - July 2005
109. Medium Term Conservancy Works
110. Engineering Assessment of 2006 Floods - Final Report - February 2006
111. Draft report on conservancy flood management modelling - May 2005
112. Draft report on conservancy flood management modelling - Model update report August 2005
200. Reports by Victor M. Ponce
201. Report of the First Mission, 13-17 March 2006
202. Report of the Second Mission, 5-13 June 2006
211. Rehabilitation of the East Demerara and Boraeserie Water Conservancies
900. Other miscellaneous data and documents
901. Guyana map 01
902. Guyana map 02 (detail)
903. Guyana Terms of Reference --- Second Mission 060531
904. Guyana Terms of Reference for Consulting 060603 - Draft