CLOSED CONDUITS I

CHAPTER 5 (2) -- ROBERSON ET AL., WITH ADDITIONS



    EXPLICIT EQUATIONS FOR PIPE FLOW

  • DARCY-WEISBACH FRICTION COEFFICIENT BASED ON RELATIVE ROUGHNESS AND REYNOLDS NUMBER:

  • f = 0.25 { log [ (ks /(3.7D)) + (5.74/Re0.9) ] } -2

  • RESTRICTED TO

  • 0.00001 < ks /D < 0.02

  • 4000 < Re < 100,000,000

  • FOR EXAMPLE, IN PROBLEM 1 EXAMPLE (CHAPTER 5-1):

  • ks /D = 0.0007

  • Re = 318,000

  • f = 0.25 { log [(0.0007/ (3.7)) + (5.74/3180000.9) ] } -2

  • f = 0.019       OK!


  • DISCHARGE BASED ON RELATIVE ROUGHNESS AND HEAD LOSS:

    A* = D1.5(g hf /L)0.5       [UNITS OF KINEMATIC VISCOSITY]

  • Q = -2.22 A* D log { (ks /(3.7D)) + (1.78 ν /A*)}

  • FOR EXAMPLE, IN PROBLEM 2 EXAMPLE (CHAPTER 5-1):

  • D = 0.2 M

  • hf/L = 0.0122

  • ks/D = 0.0007

  • ν = 1.0 × 10-6 M2/S

  • A* = 0.21.5 [(9.81) (0.0122)]0.5 = 0.03094

  • Q = -2.22 (0.03094) (0.2) × log [(0.0007/3.7) + (1.78 / 30,940)]

  • Q = 0.0496 M3/S ≅ 0.05 M3/S       OK!


  • PIPE DIAMETER BASED ON DISCHARGE, HEAD LOSS, AND ROUGHNESS:

  • B* = g hf /L

  • D = 0.66 [(ks1.25 Q 9.5 / B* 4.75) + (ν Q 9.4 / B* 5.2) ] 0.04

  • THIS EQUATION IS DIMENSIONLESS!

  • FOR EXAMPLE, IN PROBLEM 3 EXAMPLE (CHAPTER 5-1):

  • Q = 0.05 M3/S

  • hf/L = 0.0122

  • ks/D = 0.0007

  • ν = 1.0 × 10-6 M2/S

  • FROM FIG. 5-5:   ks = 0.0004 FT = 0.00012 M

  • THEN:

  • B* = 9.81 (0.0122) = 0.1197

  • D = 0.66 [(0.000121.25 0.059.5/0.11974.75) + (0.000001) 0.059.4 /0.11975.2) ] 0.04

  • D = 0.2 M.       OK!


  • SUMMARY:

  • f = 0.25 { log [ (ks /(3.7D)) + (5.74/Re0.9) ] }-2       [dimensionless coefficient: no units]

  • A* = D1.5(g hf /L)0.5       [viscosity: L2/T]

  • Q = -2.22 A* D log { (ks /(3.7D)) + (1.78 ν / A*) }       [discharge: L3/T]

  • B* = g hf /L       [acceleration: L/T2]

  • D = 0.66 [(ks1.25 Q 9.5 / B* 4.75) + (ν Q 9.4 / B* 5.2) ] 0.04       [diameter: L]

  • THESE FORMULAS ARE DIMENSIONALLY CONSISTENT!


    EXAMPLE 5-5

  • DETERMINE THE DIAMETER OF STEEL PIPE NEEDED TO DELIVER WATER (20oC) AT Q = 2 M3/S FROM A RESERVOIR AT ELEV. 60 M, TO A RESERVOIR 200 M AWAY WITH AN ELEV. 30 M. ASSUME A SQUARE-EDGED INLET AND OUTLET AND NO BENDS IN THE PIPE. ASSUME THERE ARE TWO OPEN GATE VALVES IN THE PIPE.

  • ITERATIVE SOLUTION USING HEAD LOSS EQUATION:

  • Writing the energy equation from the upper to the lower reservoir:

  • p1/γ + α1V12/(2g) + z1 = p2/γ + α2V22/(2g) + z2 + ΣhL

  • 0 + 0 + z1 = 0 + 0 + z2 + [ke + 2kv + kE+ f L/D ] V2/(2g)

  • 0 = z2 - z1 + [ke + 2kv + kE+ f L/D ] V2/(2g)

  • 0 = z2 - z1 + [ke + 2kv + kE+ f L/D ] [(Q2/A2)/2g)]

  • ASSUME

    -- ks = 0.046 MM = 0.000046 M (STEEL) (FIG. 5-5)

    -- ke = 0.5 (square-edged inlet)

    -- kv = 0.2 (open gate)

    -- kE = 1.0 (square-edged)

    -- f = 0.02

  • 0 = 30 - 60 + [0.5 + 0.4 + 1.0 + 0.02 (200)/D] ⋅ (2)2 /[(0.25πD2)2 (2 × 9.81)]

  • 30 = [1.9 + (4/D)] ⋅ [4/((0.25πD2)2(2)(9.81))]

  • 30 = [1.9 + (4/D)] ⋅ 4/[(0.252π2D4) (2) (9.81)]

  • 30 = [1.9 + (4/D)] ⋅ [0.33/D4]

  • SOLVE FOR DIAMETER D:

  • D = 0.56 M

  • A = (π/4) D2 = 0.246 M2

  • V = Q/A = 2/0.246 = 8.12 M/S

  • Re = VD/ν = 8.12 (0.56) /(0.000001) = 4,547,200.

  • f = 0.25 / {log [(ks /3.7D) + (5.74/Re0.9)]}2

  • ks /(3.7D) = 0.000046 / [(3.7) (0.56)] = 0.0000222

  • f = 0.25 / {log [0.0000222 + (5.74/4,547,2000.9)]}2

  • f = 0.25 / {log [0.0000222 + 0.000005847]}2

  • f = 0.012

  • SUBSTITUTE THIS VALUE BACK TO ENERGY EQUATION:

  • SOLVE FOR DIAMETER D:

  • D = 0.52 M

  • A = (π/4) D2 = 0.2124 M2

  • V = Q/A = 2/0.2124 = 9.42 M/S

  • Re = VD/ν = 9.42 (0.52) /(0.000001) = 4,898,400.

  • f = 0.25 / {log [(ks /3.7D) + (5.74/Re0.9)]}2

  • ks /(3.7D) = 0.000046 / [(3.7) (0.52)] = 0.0000239

  • f = 0.25 / {log [0.0000239 + (5.74/4,898,4000.9)]}2

  • f = 0.25 / {log [0.0000239 + 0.000005468]}2

  • f = 0.012       OK!


    EXAMPLE 5-6: ITERATIVE SOLUTION USING DIAMETER EQUATION (5-19)

  • ASSUME f = 0.02

  • EQUIVALENT LENGTH OF PIPE Le FOR MINOR LOSSES:

  • hL = f [(L + Le)/D] V2/(2g)

  • hL = f (L/D) V2/(2g) + f (Le/D) V2/(2g)

  • f (Le/D) V2/(2g) = [0.5 + (2×0.2) + 1.0] V2/(2g)

  • f (Le/D) = 1.9

  • FROM WHICH EQUIVALENT LENGTH OF PIPE Le

  • Le = 1.9 D/f

  • L = L + Le = 200 + 1.9 (D / 0.02) = 200 + 95 D

  • WITH hf = 30 M AND L = 200 + 95 D

  • PLUG IN DIAMETER EQUATION 5-19 AND GET D = 0.51 M BY ITERATION.

  • GET NEW Re = 5 × 106

  • GET NEW f (Eq. 5-17): f = 0.0122

  • GET NEW Le = 1.9D/0.0122 = 155.7 D

  • PLUG IN DIAMETER EQUATION 5-19 AND GET D = 0.506 M BY ITERATION.

  • GET NEW Re = 5 × 106

  • GET NEW f (Eq. 5-17): f = 0.0122

  • GET NEW Le = 1.9D/0.0122 = 156 D

  • NO SIGNIFICANT CHANGE. D = 0.51 M       OK!


    HYDRAULIC AND ENERGY GRADE LINES

  • THE LIQUID WOULD RISE TO A HEIGHT p/γ

  • THUS, HYDRAULIC GRADE LINE (HGL)

  • ENERGY GRADE LINE (EGL) IS ABOVE HGL A DISTANCE OF αV2/2g


    HINTS

  • IF VELOCITY HEAD IS ZERO, EGL AND HGL COINCIDE.

  • EGL WILL SLOPE DOWNWARD IN THE DIRECTION OF FLOW.

  • PUMP SUPPLIES ENERGY TO THE FLOW. THUS, AN ABRUPT RISE IN EGL OCCURS FROM U/S TO D/S OF PUMP.

  • TURBINE ABSORBS ENERGY FROM THE FLOW.

  • THUS, AN ABRUPT DROP IN EGL OCCURS FROM U/S TO D/S OF TURBINE.

  • GRADUAL EXPANSION AT THE OUTLET WILL CONVERT MUCH OF VELOCITY HEAD TO PRESSURE HEAD.

  • WHEN THE PRESSURE IS ZERO, THE HGL WILL COINCIDE WITH THE WATER LEVEL.

  • FOR STEADY FLOW IN A PIPE WITH UNIFORM CHARACTERISTICS, THE HEAD LOSS PER UNIT OF LENGTH (SLOPE OF EGL AND HGL) WILL BE CONSTANT.

  • IF FLOW PASSAGE CHANGES DIAMETER, THE DISTANCE BETWEEN EGL AND HGL WILL CHANGE.

  • WHEN VELOCITY INCREASES, EGL WILL INCREASE BECAUSE HEAD LOSS PER UNIT OF LENGTH INCREASES.


  • IF HGL FALL BELOW PIPE, THE PRESSURE p/γ IS NEGATIVE.

  • THIS INDICATES A PRESSURE LOWER THAN ATMOSPHERIC.

  • IF THE NEGATIVE PRESSURE REACHES (OR COMES CLOSE TO) THE VAPOR PRESSURE HEAD OF WATER (-33 FT AT 60oF) CAVITATION WILL OCCUR.

  • CAVITATION CAN CAUSE STRUCTURAL DAMAGE TO THE PIPE.

  • CAVITATION OCCURRED IN GLEN CANYON DAM DURING THE FLOOD OF JUNE 1983, WHEN THE CLOSE-CONDUIT EMERGENCY SPILLWAY WAS USED FOR THE FIRST TIME, FOLLOWING WIDESPREAD FLOODING IN THE COLORADO RIVER AS A RESULT OF THE 1983 EL NIÑO EVENT.


Glen Canyon Dam, Arizona.

  • CAVITATION OCCURRED IN TARBELA DAM, PAKISTAN, IN 1974, WHEN THE OUTLET STRUCTURES WERE USED FOR THE FIRST TIME, FOLLOWING AN EARLY UNEXPECTED FILLING OF THE RESERVOIR.


Tarbela Dam, Pakistan, the largest earth dam in the world.

  • IF PRESSURE DECREASES TO VAPOR PRESSURE AND STAYS THAT LOW, A LARGE VAPOR CAVITY CAN FORM.

  • ENGINEER SHOULD BE EXTREMELY CAUTIOUS ABOUT NEGATIVE PRESSURE HEADS IN PIPES.


    HEAD-DISCHARGE RELATIONS FOR PUMP OR TURBINE

  • HEADS hp AND ht ARE A FUNCTION OF THE DISCHARGE FOR A MACHINE (PUMP OR TURBINE) OPERATING AT A GIVEN SPEED.

  • TYPICAL PERFORMANCE IS GIVEN IN FIG. 5-10.

  • PERFORMANCE OR CHARACTERISTIC OF MACHINE: HEAD IS INVERSELY RELATED TO DISCHARGE FOR A GIVEN RPM OF MACHINE.


  • OTHER PERFORMANCE CURVES, SUCH AS EFFICIENCY AND POWER VS DISCHARGE ARE INCLUDED WITH MACHINE SPECIFICATIONS.

  • IF Q IS GIVEN, THE HEAD IS TAKEN DIRECTLY FROM THE PERFORMANCE CURVE.

  • IF H IS GIVEN, A SIMULTANEOUS SOLUTION OF THE ENERGY EQUATION AND THE PERFORMANCE CURVE WILL YIELD Q.

  • MORE ON CHAPTER 8.


    BRANCHING PIPES

  • CONSIDER FIG 5-11: THREE RESERVOIRS CONNECTED BY A BRANCHED PIPE SYSTEM.


  • THE PROBLEM IS TO DETERMINE THE DISCHARGE IN EACH PIPE AND THE HEAD AT D.

  • THERE ARE FOUR UNKNOWNS:

  • VAD

  • VBD

  • VDC

  • pD

  • A SOLUTION IS OBTAINED BY SOLVING THE ENERGY EQUATION FOR THE PIPES (NEGLECTING VELOCITY HEADS AND INCLUDING ONLY PIPE LOSSES) AND THE CONTINUITY EQUATION.

  • zA = zD + pD/γ + fAD (LAD /DAD ) VAD2 / (2g)

  • zB = zD + pD/γ + fBD (LBD /DBD ) VBD2 / (2g)

  • zD + pD/γ = fDC (LDC /DDC ) VDC2 / (2g)

  • VAD AAD + VBD ABD = VDC ADC

  • X = VAD AAD + VBD ABD - VDC ADC

  • ITERATIVE METHOD:

  • FIRST ASSUME zA = zD + pD/γ      (NO FLOW IN AD, VAD = 0)

  • pD/γ = zA - zD

  • THEN DETERMINE VBD, VDC, QBD AND QDC (PIPE ROUGHNESS, DIAMETER, LENGTH, AND AREAS ARE KNOWN)

  • CALCULATE X

  • IF X IS POSITIVE , pD/γ WILL HAVE TO BE INCREASED; FLOW MUST BE DIRECTED TO RESERVOIR A.

  • IF X IS NEGATIVE , pD/γ WILL HAVE TO BE DECREASED; FLOW MUST BE DIRECTED OUT OF RESERVOIR A.

  • NEXT TRY ANOTHER pD/γ UNTIL X = 0.


    PARALLEL PIPES

  • CONSIDER A PIPE THAT BRANCHES INTO TWO PARALLEL PIPES AND THEN REJOINS.


  • THE PROBLEM MAY BE TO DETERMINE THE DIVISION OF FLOW IN EACH PIPE, GIVEN THE TOTAL FLOW RATE.

  • HEAD LOSS MUST BE THE SAME IN EACH PIPE: hL1 = hL2

  • f1 (L1/D1) V12/(2g) = f2 (L2 /D2) V22/(2g)

  • (V1/V2) 2 = (f2 L2 D1) / (f1 L1 D2)

  • V1/V2 = [(f2 L2 D1) / (f1 L1 D2)] 1/2

  • IF f1 AND f2 ARE KNOWN, THE DIVISION OF FLOW CAN BE READILY DETERMINED.

  • Q = V1A1 + V2A2

  • Q/V2 = (V1/V2) A1 + A2

  • V2 = Q / [(V1/V2) A1 + A2]

  • Q2 = V2A2

  • Q2 = Q A2/ [(V1/V2) A1 + A2]

  • Q2 = Q / { [(V1/V2) (A1/A2)] + 1}

  • Q2 = Q / { [(V1/V2) (D1/D2)2] + 1}

  • Likewise:

  • Q1 = Q / { { 1 / [(V1/V2) (A1/A2)]}   + 1 }

  • Q1 = Q / { { 1 / [(V1/V2) (D1/D2)2]}   + 1 }

  • a = (V1/V2) (D1/D2)2

  • V1/V2 = [(f2 L2 D1) / (f1 L1 D2)] 1/2

  • a = [(f2/f1) (L2/L1)]1/2 (D1/D2)5/2

  • Q1 = Q / [(1/a) + 1] = aQ/(a + 1)

  • Q2 = Q / (a + 1)

  • Q = Q1 + Q2        OK!

  • IF FRICTION FACTORS ARE FUNCTIONS OF Re, SOME TRIAL AND ERROR MAY BE REQUIRED.


    PIPE NETWORKS

  • THE MOST COMMON PIPE NETWORK SYSTEMS ARE THE WATER DISTRIBUTION SYSTEMS FOR MUNICIPALITIES.

  • SOURCES: WATER ENTERING THE NETWORK

  • LOADS: WATER OUTFLOWING THE NETWORK

  • FIG. 5-16 SHOWS A SIMPLIFIED SYSTEM WITH 2 SOURCES AND 7 LOADS.


  • ENGINEER IS OFTEN ENGAGED TO DESIGN THE ORIGINAL SYSTEM OR TO RECOMMEND AN ECONOMICAL EXPANSION TO THE NETWORK.

  • THE ENGINEER IS REQUIRED TO PREDICT PRESSURES THROUGHOUT THE NETWORK FOR VARIOUS OPERATING CONDITIONS, THAT IS, FOR VARIOUS COMBINATIONS OF SOURCES AND LOADS.

  • THE SOLUTION MUST SATISFY THREE BASIC REQUIREMENTS:

    1. CONTINUITY: THE FLOW INTO A JUNCTION MUST EQUAL THE FLOW OUT OF THE JUNCTION.

    2. SINCE PRESSURE MUST BE CONTINUOUS, THE HEAD LOSS BETWEEN ANY TWO JUNCTIONS MUST BE THE SAME, REGARDLESS OF THE PATH TAKEN FROM ONE JUNCTION TO THE OTHER.

    3. THE FLOW AND HEAD LOSS MUST BE CONSISTENT WITH THE APPROPRIATE VELOCITY HEAD EQUATION.

  • TRIAL AND ERROR SOLUTION.


    HARDY CROSS METHOD

  • STEPS:

    -- FIRST, FLOW IS DISTRIBUTED THROUGH THE NETWORK SO THAT CONTINUITY IS SATISFIED.

    -- FIRST GUESS WILL NOT SATISFY REQUIREMENT OF EQUAL HEAD LOSS IN LOOP.

    -- A DISCHARGE CORRECTION IS APPLIED TO YIELD A ZERO NET HEAD LOSS AROUND THE LOOP.



  • HEAD LOSS IS:

  • hL = f (L/D) (V2/2g)

  • hL = f (L/D) [Q2/(2gA2)]

  • hL = f (L/D) [8Q2/(gπ2 D4)]

  • hL = [(8 f L) /(gπ2D5)] Q2

  • THE HEAD LOSS IS PROPORTIONAL TO THE SQUARE OF THE DISCHARGE.

  • hL = k Q2

  • k = (8 f L) /(gπ2D5)

  • ∑ hL clockwise = ∑ hL counterclockwise

  • ∑ k Q 2 clockwise = ∑ k Q 2 counterclockwise

  • ∑ k Qc2 = ∑ k Qcc2

  • A ΔQ WILL HAVE TO BE APPLIED TO SATISFY THE HEAD LOSS REQUIREMENT.

  • CASE 1:   IF ∑ k Qc2 > ∑ k Qcc2

    ΔQ IS SUBTRACTED FROM THE CLOCKWISE FLOWS AND ADDED TO THE COUNTERCLOCKWISE FLOWS.

  • CASE 2:   IF ∑ k Qc2 < ∑ k Qcc2

    ΔQ IS SUBTRACTED FROM THE COUNTERCLOCKWISE FLOWS AND ADDED TO THE CLOCKWISE FLOWS.

  • ASSUME THAT THE SIGN OF ΔQ IS DETERMINED BY THE FIRST CASE:

  • ∑ k (Q c - ΔQ) 2 = ∑ k (Qcc + ΔQ) 2


  • IN GENERAL:

  • ∑ k (Q c - ΔQ) n = ∑ k (Qcc + ΔQ) n

  • EXPANDING THE SUMMATION ON EITHER SIDE, AND INCLUDING ONLY TWO TERMS OF THE SERIES EXPANSION:

  • (Qc - ΔQ) n = Qcn - nQcn-1 ΔQ

  • EXAMPLE WITH n = 2, Qc = 100, ΔQ = 1:

  • (100 - 1)2 = 9801 ≅ [10000 - 2 × 100 × 1 ] = 9800

  • ∑ k (Qcn - nQcn-1 ΔQ) = &sum k (Qccn + nQccn-1 ΔQ)

  • ΔQ = (∑ k Qcn - &sum k Qccn) / (∑ nk Qcn-1 + ∑ nk Qccn-1)              (EQ. 5-29)

  • IN THIS FORMULA, WHATEVER THE SIGN OF ΔQ IS, IT SHOULD BE SUBTRACTED FROM THE CLOCKWISE FLOWS!

  • THE CORRECTION IS APPLIED IN A COUNTERCLOCKWISE SENSE!

  • EXPERIENCE SHOWS THAT FEWER TRIALS ARE REQUIRED IF   (0.6 ΔQ)   IS USED INSTEAD OF   ΔQ (EQ. 5-29).


    EXAMPLE

  • FOR THE GIVEN SOURCE AND LOADS SHOWN IN FIG. A, WHAT IS THE DISTRIBUTION OF FLOWS IN THE NETWORK AND WHAT IS THE PRESSURE AT THE LOAD POINTS IF THE PRESSURE AT THE SOURCE IS 60 PSI. ASSUME HORIZONTAL PIPES AND f = 0.012.


  • SOLUTION:

  • CALCULATION OF k FOR ALL PIPES:

  • k = (8f L) /(gπ2D5)

  • kAB = [8(0.012)(1000)] /[(32.2)(3.1416)2 (2)5] = 0.00944

  • LIKEWISE:

  • kBC = 0.3021; kBD = 2.2940; kAD = 1.0590; kDE = 0.3021; kCE = 0.7516.

  • ASSUME:

  • QAB = 10 CFS;

  • QAD = - 5 CFS (cc);

  • QBD = 0 CFS;

  • QBC = 10 CFS;

  • QDE = - 5 CFS (cc);

  • QCE = 0 CFS.

  • IF SIGNS ARE ASSUMED, ΔQ SHOULD BE SUBTRACTED FROM ALL FLOWS, C, CC, AND NO FLOW.

  • FOR n = 2, FORMULA FOR ΔQ SIMPLIFIES TO:

  • ΔQ = (∑ k Qc2 - &sum k Qcc2) / (∑ 2k Qc + ∑ 2k Qcc)

  • FOR SIMPLE LOOP, FORMULA FOR ΔQ SIMPLIFIES TO:

  • ΔQ = (k Qc2 - k Qcc2) / (2k Qc + 2k Qcc)


    FIRST TRIAL

  • LOOP ABD:

    PIPE kQ2 2kQ
    AB (c) 0.944 0.189
    AD (cc) -26.475 10.59
    BD (no flow) 0.000 0.000
    -25.531 10.78

  • ΔQ = -25.531/10.78 = -2.4

  • ΔQ TO BE SUBTRACTED FROM ALL FLOWS.

  • THEN:

  • QAB = 10 - (-2.4) = 12.4

  • QAD = -5 - (-2.4) = - 2.6

  • QBD = 0 - (-2.4) = 2.4

  • LOOP BCDE:

    PIPE kQ2 2kQ
    BC (c) 30.21 6.042
    BD (no flow) 0.000 0.000
    CE (no flow) 0.000 0.000
    DE (cc) -7.55 3.02
    22.66 9.062

  • ΔQ = 22.66/9.062 = 2.5

  • ΔQ TO BE SUBTRACTED FROM ALL FLOWS.

  • THEN:

  • QBC = 10 - 2.5 = 7.5

  • QCE = 0 - 2.5 = - 2.5

  • QBD = -2.4 (from loop ABD) - 2.5 = - 4.9

  • QDE = -5 - 2.5 = - 7.5

  • SUMMARY:

  • QAB = 12.4

  • QAD = - 2.6

  • QBD = 4.9 (-4.9)     (shared in the loop)

  • QBC = 7.5

  • QCE = - 2.5

  • QDE = - 7.5



    SECOND TRIAL

  • LOOP ABD:

    PIPE kQ2 2kQ
    AB (c) 1.451 0.234
    AD (cc) -7.159 5.507
    BD (c) 55.079 22.481
    49.371 28.222

  • ΔQ = 49.371/28.222 = 1.7

  • ΔQ TO BE SUBTRACTED FROM ALL FLOWS.

  • QAB = 12.4 - 1.7 = 10.7

  • QAD = -2.6 - 1.7 = - 4.3

  • QBD = 4.9 - 1.7 = 3.2

  • LOOP BCDE:

    PIPE kQ2 2kQ
    BC (c) 16.993 4.5315
    BD (cc) -55.079 22.4812
    CE (cc) -4.6975 3.7580
    DE (cc) -16.993 4.5315
    -59.7765 35.3022

  • ΔQ = -59.7765/35.3022 = -1.7

  • ΔQ TO BE SUBTRACTED FROM ALL FLOWS.

  • QBC = 7.5 - (-1.7) = 9.2

  • QBD = - 3.2 (from loop ABD) - (-1.7) = - 1.5

  • QCE = -2.5 - (-1.7) = - 0.8

  • QDE = - 7.5 - (-1.7) = - 5.8

  • SUMMARY:

  • QAB = 10.7

  • QAD = - 4.3

  • QBD = 1.5 (-1.5)     (shared in the loop)

  • QBC = 9.2

  • QCE = - 0.8

  • QDE = - 5.8


    THIRD TRIAL

  • LOOP ABD:

    PIPE kQ2 2kQ
    AB (c) 1.0808 0.2020
    AD (cc) -19.581 9.1074
    BD (c) 5.1615 6.882
    -13.3387 16.1914

  • ΔQ = -13.3387/16.1914 = -0.8

  • ΔQ TO BE SUBTRACTED FROM ALL FLOWS.

  • QAB = 10.7 - (-0.8) = 11.5

  • QAD = -4.3 - (-0.8) = - 3.5

  • QBD = 1.5 -(-0.8) = 2.3

  • LOOP BCDE:

    PIPE kQ2 2kQ
    BC (c) 25.570 5.5586
    BD (cc) -5.1615 6.8820
    CE (cc) -0.4810 1.2026
    DE (cc) -10.163 3.5043
    9.7645 17.1475

  • ΔQ = 9.7645/17.1475 = 0.5

  • ΔQ TO BE SUBTRACTED FROM ALL FLOWS.

  • QBC = 9.2 - 0.5 = 8.7

  • QBD = - 2.3 (from loop ABD) - 0.5 = - 2.8

  • QCE = - 0.8 - 0.5 = - 1.3

  • QDE = - 5.8 - 0.5 = - 6.3

  • SUMMARY:

  • QAB = 11.5

  • QAD = - 3.5

  • QBD = 2.8 (-2.8)     (shared in the loop)

  • QBC = 8.7

  • QCE = - 1.3

  • QDE = - 6.3


    FOURTH TRIAL

  • LOOP ABD:

    PIPE kQ2 2kQ
    AB (c) 1.248 0.2171
    AD (cc) -12.972 7.413
    BD (c) 17.985 12.846
    6.261 20.4761

  • ΔQ = 6.261/20.4761 = 0.3

  • ΔQ TO BE SUBTRACTED FROM ALL FLOWS.

  • QAB = 11.5 - 0.3 = 11.2

  • QAD = - 3.5 - 0.3 = - 3.8

  • QBD = 2.8 - 0.3 = 2.5

  • LOOP BCDE:

    PIPE kQ2 2kQ
    BC (c) 22.866 5.2565
    BD (cc) -17.984 12.846
    CE (cc) -1.2702 1.9542
    DE (cc) -11.990 3.8065
    -8.3742 23.8632

  • ΔQ = - 8.3742/23.8632 = - 0.3

  • ΔQ TO BE SUBTRACTED FROM ALL FLOWS.

  • QBC = 8.7 - (-0.3) = 9.0

  • QBD = - 2.5 (from loop ABD) - (-0.3) = - 2.2

  • QCE = - 1.3 - (-0.3) = - 1.0

  • QDE = - 6.3 - (-0.3) = - 6.0

  • SUMMARY:

  • QAB = 11.2

  • QAD = - 3.8

  • QBD = 2.2 (-2.2)     (shared in the loop)

  • QBC = 9.0

  • QCE = - 1.0

  • QDE = - 6.0

  • FINAL VALUES (BOOK PAGE 255):

  • QAB = 11.4

  • QAD = - 3.6

  • QBD = 2.4 (-2.4)     (shared in the loop)

  • QBC = 9.0

  • QCE = - 1.0

  • QDE = - 6.0



    PRESSURES AT THE LOAD POINTS C AND E

  • pC = pA - γ (kAB QAB2 + kBC QBC2)

  • pC (lb/ft2) = 60 lb/in2 × 122 (in2/ft2) - 62.4 lb/ft3 [(0.00944 × 11.42) + (0.3021 × 9.02)] ft

  • pC (lb/ft2) = 7037

  • pC (lb/in2) = 48.9

  • pE = pA - γ (kAD QAD2 + kDE QDE2)

  • pE (lb/ft2) = 60 lb/in2 × 122 (in2/ft2) - 62.4 lb/ft3 [(1.059 × 3.6 2) + (0.3021 × 6.02)] ft

  • pE (lb/ft2) = 7105

  • pE (lb/in2) = 49.3


091013