SPRING 2009 - MIDTERM 2 - SOLUTION
Drainage area = 60 ha Rainfall intensity = 30 mm/hr Runoff coefficient = 0.95 Peak discharge Qp = 0.95 × 30 mm/hr × 60 ha Qp = 0.95 × 30 mm/hr × 0.001 m/mm × (1/3600) hr/s × 60 ha × 10,000 m2/ha Qp = 4.75 m3/s ANSWER. Problem 2 090407
Rainfall intensity = 30 mm/hr
Runoff coefficient = 0.95
Peak discharge Qp = 0.95 × 30 mm/hr × 60 ha
Qp = 0.95 × 30 mm/hr × 0.001 m/mm × (1/3600) hr/s × 60 ha × 10,000 m2/ha
Qp = 4.75 m3/s ANSWER. Problem 2
Problem 2